Karnataka Textile Mill — Open Access Approval in 45 Days
A large textile manufacturer in Karnataka had been paying HT tariff of ₹7.85/unit. Their in-house team had struggled with open access approvals for 8 months. Instant Reach secured STOA approval within 45 days and transitioned them to third-party renewable power at ₹5.60/unit.
Maharashtra Industrial Conglomerate — 25-Year Bankable Solar PPA
A diversified industrial group in Maharashtra needed a long-term, lender-ready PPA for their 10 MW captive solar plant. Instant Reach structured a 25-year fixed-rate agreement at ₹2.85/unit — well below their prevailing DISCOM tariff — and supported due diligence for project financing.
Rajasthan IPP — Evacuation NOCs for 80 MW Wind Project
An Independent Power Producer developing an 80 MW wind project in Rajasthan needed simultaneous evacuation approvals from RRVPNL, SLDC, and forest department. Instant Reach coordinated all three tracks in parallel, securing approvals within 90 days and keeping the project on its commissioning schedule.
Tamil Nadu Auto Parts Manufacturer — IEX Trading Portfolio
A high-tension auto components manufacturer in Tamil Nadu with 4 MW contracted demand was paying peak HT tariff. Instant Reach designed a hybrid procurement strategy using Day-Ahead Market and Green Term-Ahead Market on IEX, blended with a short-term PPA, cutting effective per-unit cost by 22%.